Eng. Peter Otieno · 2 May 2026 · 5 min read
Nameplate production figures rarely reflect what actually arrives at a treatment works. Shift patterns, cleaning cycles and seasonal product mix produce peaks that a design based on annual averages will not absorb.
A four-to-six week characterisation programme sampling across shifts and cleaning cycles gives a defensible design basis, including the diurnal and weekly peaking factors that determine balancing tank volume.
The cost of characterisation is a small fraction of the cost of retrofitting a plant that cannot meet its discharge licence — and it materially strengthens the compliance case if a discharge is ever queried.